With the competitive capacity of management, labor and
equipment, FS Construction JSC., has received a package for construction of
large open canal, which is parallel with the 34m East Road of Dinh Vu
Industrial Zone, and next to the tire manufactory, Bridgestone. The value of
this project is nearly 20 billions Viet nam dong.

The project has been carried out by us in 6 months by
the best team of staffs and technical workers are trained beside regular and
modern equipment which invested by FS itself. At the time of construction, the
company has mobilized 02 excavators, 03 trucks from 5 to 15 tons.
The company also has reliable partners willing to
provide capital, machinery, labor and suppliers of construction materials to
meet the strict technical standards of the owner (gabion, sand , stone, cement,
sticky soil, bamboo piles ...)
This project started in early December 2012 and completed
and handed over in the April of 2013 - on schedule and technical requirements
required by the investor.
FS JSC.